Project facts

What is proposed.

A large-scale data center development in Duchesne County, described in public filings as being near Wells Draw Road and connected to supporting energy and water infrastructure.

UpdatedMay 25, 2026

Project summary

The Nine Mile Data findings report says Energence Utah, LLC plans to develop a large-scale data center complex approximately six miles southwest of Myton, Utah. The report describes the project as using about 475 acres of a larger leased area and targeting operations by 2029.

The same county/project narrative describes perimeter security, spill-prevention measures, a transportation plan, and a project life of at least 50 years.

Source: county findings report

Data-center applicant

Nine Mile Data, LLC is named in the conditional-use permit materials and public notices for the data center.

Developer named in narrative

Energence Utah, LLC is named in the findings report narrative as the entity planning the data-center complex.

Engineering / filing support

County materials say Jones & DeMille Engineering submitted materials on behalf of Energence Utah.

Related project entities

Wells Draw Energy LLC appears in solar and natural-gas power plant filings. reWater LLC appears in produced-water facility filings.

Review related filings

LLC and company roles

Public records name multiple LLCs rather than one single developer. Nine Mile Data, LLC is the data-center permit name. Energence Utah, LLC is the entity described in county narratives as planning the data-center complex and related power facilities. Wells Draw Energy LLC is used for the solar and natural-gas permits. reWater LLC is used for the produced-water facility.

Elio Energy Group LLC appears in project plan sheets and outside renewable-energy-development materials. Florida Sunbiz lists Elio Energy Group LLC as an active Florida limited liability company, with its 2026 annual report filed March 11, 2026. Redelfi and Redelio materials describe Elio as a U.S. utility-scale renewable project developer and partner in a battery-storage development joint venture.

The reviewed public filings do not fully explain the ownership or control relationship among Elio Energy Group LLC, Energence Utah, LLC, Nine Mile Data, LLC, Wells Draw Energy LLC, and reWater LLC. Until a filing or direct statement clarifies that chain, this site describes each entity by the role it is named as having in public records.

Sources: county filings, Utah Public Notice, Florida Sunbiz, Redelfi/Redelio materials
Concept visualization of the proposed data center campus in a Uintah Basin landscape
Concept visualization only, added to help the public understand the type of campus-scale facility described in county filings.
Project image

A campus-scale industrial technology project.

County/project narrative describes a large-scale data center complex using roughly 475 acres within a larger leased area. Final drawings, equipment placement, and visual screening should be published as they become available.

Scale described in filings
$10BEstimated investment
1,000Peak construction workers described in narrative
200Long-term data-center jobs described in narrative
50+Years minimum facility lifespan described in narrative