Public schedule

Known public timeline.

Dates below come from county findings, public notices, and local reporting available as of May 1, 2026.

UpdatedMay 27, 2026

Project lifecycle

From application to operation.

One track from the first county filing through the projected build-out. Dated steps come from county findings, public notices, and local reporting; future steps are estimates from the project narrative and are marked projected — all contingent on approvals. Hover a step to magnify it; on a touch screen, tap a step to open it.

  1. Applications submitted

    County materials say land-use applications for the data center and the related Wells Draw Energy and reWater permits were submitted and deemed complete.

    Site location and access-route map for the Nine Mile Data project, southwest of Myton, Utah
    Site location & access-route map — Nine Mile Data submittal exhibit.
  2. Public notices published

    Public hearing notices for the Nine Mile Data conditional-use permit were published in the Uintah Basin Standard on March 18 and 25, ahead of the April 2 Planning Commission hearing.

    Duchesne County public hearing notice for the Nine Mile Data conditional-use permit
    Public hearing notice — published Mar. 18 & 25, 2026 (Uintah Basin Standard).
  3. CUPs approved

    At its April 2 hearing the Duchesne County Planning Commission considered and granted conditional-use permits for the data center and the adjacent solar (reWater) and natural-gas (Wells Draw Energy) plants.

    Duchesne County Planning Commission meeting minutes, April 2, 2026
    Planning Commission minutes — Duchesne County, Apr. 2, 2026.
  4. Appeals denied

    Resident appeals of the approvals were heard by the County Commission and denied, one for lack of standing. The county permits stand; Basin Now reported the denials on April 28.

    Duchesne County Commission approved meeting minutes, April 27, 2026
    County Commission minutes (approved) — combined meeting, Apr. 27, 2026.
    Duchesne County Commission minutes page recording the appeal of the Wells Draw Energy natural-gas permit, April 27, 2026
    Minutes (draft) — appeal of the natural-gas permit (p. 10 of 19).
  5. Construction begins

    The project narrative says Elio Energy plans to begin construction in 2027 — contingent on final approvals and permits.

  6. Build complete · operational

    The narrative targets operation before 2030, around 2029; the filings show some timing inconsistencies.

  7. Facility lifespan

    The narrative describes a facility life of at least 50 years from the start of operation.